Monday, December 26, 2011

Daily Report : December 26, 2011





Monday, December 26, 2011

Weather       :Cloudy
Tempeature    :29°C - 34°C
Humidity      :79%
Wind Direction:South Wind Direction
Wind Speed​​    :10km/h


North Walkways

Problem   : skirting ceramics has not been installed
Couse     : - ceramics have not arrived at the site
            - not unloading cargo ships  
Action by : Owner & Contractor
                                                                
Ceramic Floor North Walkways



Widening of the main ladder

Problem   : can not be completed until the end of the ladder
Couse     : underground electric cables has not installed & 
            procurement yet.
Action by : procurement by Owner



Ladder Work and Railling Colomn Structure
Ladder Work

Slab Railling Work


Brick Railling





Painting Roof End Work


Ceramic Floor at Kitchen


Ceramic Floor at Kitchen