Monday, December 26, 2011
Weather :Cloudy
Tempeature :29°C - 34°C
Humidity :79%
Wind Direction:South Wind Direction Wind Speed :10km/h
North Walkways
Problem : skirting ceramics has not been installed
Couse : - ceramics have not arrived at the site
- not unloading cargo ships
Action by : Owner & Contractor
 |
| Ceramic Floor North Walkways |
|
|
Widening of the main ladder
Problem : can not be completed until the end of the ladder
Couse : underground electric cables has not installed &
procurement yet.
Action by : procurement by Owner
 |
| Ladder Work and Railling Colomn Structure |
 |
| Ladder Work |
 |
| Slab Railling Work |
 |
| Brick Railling |
 |
| Painting Roof End Work |
 |
| Ceramic Floor at Kitchen |
 |
| Ceramic Floor at Kitchen |